There’s an interesting point in almost every hotel renovation where the project feels very real, even though nobody has started construction yet.

There are drawings on the table. Someone is asking when the first floor can come offline. The hotel has a group arriving in six weeks. A vanity has a longer lead time than expected. Engineering wants to know when the water will be shut off. Somebody needs to figure out where two truckloads of furniture are going when they arrive.

The guestrooms still look exactly the same.

The renovation has already started.

That stretch before demolition is preconstruction planning, and in a hotel, there can be a lot to work through.

At Axis Hospitality Construction, we’ve done enough renovations over the years to know that preconstruction doesn’t make every problem disappear. Construction doesn’t work that way. Existing buildings surprise you. Deliveries move. Schedules change. Somebody opens a wall and finds something nobody expected.

The goal is to get as many of the questions we can answer out on the table while we still have room to work through them.

1. Turn the Drawings Into the Actual Scope

A set of drawings can make a renovation look pretty clean.

Remove this vanity. Install this one.

Replace the corridor lighting.

New wallcovering here. New flooring there.

Then you walk the property.

Maybe replacing those corridor fixtures involves getting above a ceiling that wasn’t expected to come down. The new vanity changes the plumbing location. Existing conditions differ from one guestroom stack to another. Something installed during the last renovation never made it onto the drawings.

This is where preconstruction planning starts becoming physical.

Walk the guestrooms. Open the electrical rooms. Look at the loading dock. Get above ceilings where appropriate. Talk with engineering. Compare what’s drawn with what’s actually there.

We’ve written before about how a simple PIP line item can lead further into a building than it first appears. “Upgrade the corridor lighting” can eventually involve fixtures, wiring, drywall, patching, and painting. (Read more here: 5 Common Hotel PIP Mistakes (And How to Avoid Them).)

Finding that out while everyone is sitting around a table gives you options.

Finding it out after the corridor is already under construction gives you a much shorter conversation.

2. Figure Out How Construction and the Hotel Will Share the Building

If you’re renovating an office building that’s completely empty, you have one kind of schedule.

A hotel that is still checking in guests every afternoon gives you another.

Maybe we start on the fourth floor while the hotel sells rooms on three, two, and one. When four is finished and returned to inventory, construction moves down.

That sounds simple enough written on a schedule.

Now add:

  • demolition noise
  • guest elevators
  • service elevators
  • housekeeping
  • material deliveries
  • employee access
  • temporary barriers
  • utility shutdowns
  • weddings
  • conventions
  • weekend occupancy
  • rooms that need to come back online

This is why construction phasing becomes such a large part of hotel preconstruction planning.

One of the things I say fairly often about hospitality construction is that the construction itself isn’t always the complicated part. The challenge is everything happening around it: the GM, noise complaints, FF&E deliveries, a fast schedule, and moving through an operating property one floor at a time. (Read more here: The Art of Phased Hotel Renovation: Step-by-Step Guide to Keeping Your Hotel Open and Profitable.)

Before we start, we want to understand how those two worlds are going to occupy the same building.

Axis provides and assists with preconstruction planning for hotels.

3. Build the Schedule Around the Rooms the Hotel Needs Back

Every construction project has a schedule.

Hotels add another question:

When can I sell the rooms again?

That changes how you look at the hotel renovation timeline.

Let’s say 25 rooms are taken offline. Demolition moves quickly. Flooring is installed. Painting is finished. The bathrooms are complete.

Then three sconces haven’t arrived.

Those rooms may look 98% finished when you walk through them. From the hotel’s point of view, they’re still out of order.

During the preconstruction process, it helps to work backward from turnover.

When does ownership need the floor back?

When does punch need to happen?

When does FF&E installation need to be complete?

When do the finishes need to be done?

When does each trade need to get through the rooms?

When does the material have to be on property for all of that to happen?

A hotel construction schedule starts looking different when the finish line is a sellable guestroom instead of a percentage-complete report.

4. Get Procurement Into the Conversation Early

Furniture, fixtures, finishes, equipment, and specialty materials all operate on their own clocks.

Some clocks are pretty dependable.

Others seem to have a personality of their own.

One of the procurement professionals I talked with on the Axis Hospitality Podcast gave a good example. An owner might initially say they want everything delivered in January. The construction schedule shifts and the property really needs it in March. Now the product is sitting somewhere for two months, somebody is paying for warehousing, and it will eventually have to be handled again.

Late material creates problems.

Very early material can create different problems.

During preconstruction planning, we can start asking some fairly basic questions that become very important later:

When should this arrive?

Where is it going?

How much can the hotel physically receive?

Are we installing floor by floor?

Is the product arriving by container, truckload, or individual shipment?

Where can it be staged without interfering with guests or hotel operations?

What has a long enough lead time that it needs attention now?

Those aren’t particularly glamorous questions.

They become pretty interesting when a semi-truck is sitting at the loading dock.

For more information about procurement challenges, take a look at: 7 Costly Hotel Furniture Suppliers Mistakes Smart Owners Avoid.

5. Get Design, Budget, Procurement, and Construction Talking

There’s a point during design where a beautiful idea eventually has to become a real object that somebody can buy, ship, carry into the building, and install.

That transition can get expensive.

I had a guest on the podcast use the example of a fully teak custom headboard that could cost around $7,000 per room. The design may look fantastic. Multiply it across a hotel and ownership can suddenly be looking at a very different budget. His approach is to bring manufacturing and procurement realities into design conversations earlier, while there is still room to make decisions thoughtfully.

That’s a useful way to think about the preconstruction phase in general.

The designer understands the vision.

Ownership understands the business plan and budget.

Procurement understands lead times and manufacturing.

The contractor understands the existing building and what installation will require.

The hotel understands how the property operates.

Getting those people into the same conversation early can uncover things that wouldn’t necessarily show up if everyone stayed in their own lane.

Sometimes the original design works exactly as planned.

Sometimes a small change makes it easier to manufacture.

Sometimes an alternate material makes more sense.

Sometimes everyone decides the expensive detail is worth every penny and keeps it.

At least now it’s a deliberate decision.

To learn more, read: 5 Avoidable Setbacks That Start with Skipping the Hotel Room Model.

6. Spend Time With the People Who Already Know the Building

Hotel engineering can save a contractor a lot of walking.

They know where the shutoffs are.

They know which guestroom has had the same plumbing issue three times.

They may know why an electrical panel doesn’t quite match an old drawing. They know which storage room is actually available, when deliveries become a problem, and which elevator can reasonably be shared with construction.

One longtime hospitality electrician described his approach to me this way: he treats the hotel engineer as the person whose building it is. The electrician is there temporarily. The engineer will still be taking care of the property after construction leaves.

That mindset belongs in preconstruction planning.

A good preconstruction meeting shouldn’t only be contractors talking to contractors.

The general manager may understand upcoming occupancy.

Engineering knows the physical plant.

Operations understands guest movement.

Housekeeping knows when corridors and guestrooms are busiest.

Food and beverage may have events that change access to part of the building.

Getting those details before the job starts can make the eventual plan much more realistic.

7. Work Through the Boring Logistics Before They Become Interesting

Parking.

Dumpsters.

Staging.

Keys.

Badges.

Elevators.

Loading docks.

Temporary storage.

Working hours.

Dust protection.

Crew entrances.

Material routes.

Trash removal.

None of these will be the photograph anyone posts when the renovation is finished.

They’re still part of the pre construction checklist.

Hotels have limited space, and the contractor usually doesn’t get unlimited use of it. Guests still need parking. Housekeeping still needs service elevators. The receiving dock is receiving things for the hotel too. Back-of-house hallways are being used by employees while construction carts are moving through the building.

A longtime electrical partner once described what happens after a contractor develops a good working relationship with hotel engineering. Suddenly someone tells you where you can park, where materials can be stored, or calls when the truck arrives so the crew can get downstairs and unload it.

Those seem like tiny details when you’re sitting in a conference room months earlier.

At 7:00 a.m. with twelve people waiting to unload material, they don’t feel tiny anymore.

Preconstruction Planning Doesn’t End With a Perfect Plan

I’ve never been involved in a hotel renovation where the plan survived exactly as it was written on day one.

I’d be suspicious if somebody told me they had.

There are too many moving pieces.

A manufacturer changes a lead time. The hotel books unexpected business. An existing condition shows up behind a wall. Ownership changes a finish. An inspection moves. The first floor takes three days longer and everything behind it needs to slide.

Good preconstruction management gives the team something solid to adjust from.

You know what the hotel needs.

You know how the project is phased.

You know which materials control the schedule.

You know who needs to be involved when something changes.

And you have hopefully already had a few of the conversations that are much harder to have when demolition is underway and 30 rooms are sitting out of inventory.

At Axis Hospitality Construction, our preconstruction planning is built around the realities of renovating hotels: existing buildings, operating properties, phased guestrooms, procurement, design coordination, and the people who still need to run the hotel while we’re there.

The hammers will come soon enough.

There is plenty to do before they do.

When you’re just starting to consider the preconstruction phase of your renovation, that’s the best time to call us. Reach out to us today!

 