Residence Inn Tampa Westshore, Tampa, FL

Project Overview

Hotel Name: Residence Inn by Marriott Tampa Westshore

Location: Tampa, FL

Hotel Class: Extended Stay / 3-star 

Year Renovated: 2024

Scope: Full property renovation (guest rooms, bathrooms, corridors, public spaces, back-of-house areas, exterior elements, and parking lot)

Services Provided: Demolition, flooring upgrades, millwork, plumbing and electrical overhauls, FF&E installation and warehousing, exterior repairs, parking lot repairs, restriping, resealing, custom barn door, design and procurement agent support

The The Challenges

In 2024, our client acquired Residence Inn Tampa Westshore. The busy 160-room hotel serves business travelers and tourists near Tampa International Airport –  and the property needed a comprehensive renovation. 

Marriott’s PIP required work to meet brand standards, and it all had to be done by December 2024 to capture Florida’s winter season. They brought Axis in during due diligence, before they closed on the property. 

We walked the site with SVP of Development and the Owner’s Representative to assess what Marriott’s PIP required and what it would cost. 

Our assessment revealed the scope would be complex and time-sensitive. Marriott required tub-to-shower conversions across the property, and the exterior repairs and parking lot work needed a detailed evaluation before we could provide accurate costs.

Hotel Renovation Projects

What We Did

to Solve Them

Our approach tackled both the pre-acquisition unknowns and the complexities of construction.

Pre-Acquisition Budget Forecasting 

We developed a preliminary budget based on Marriott's PIP requirements. It accounted for unknowns like the extent of exterior repairs and parking lot work. Our site assessment identified the 113 tub-to-shower conversions and evaluated EIFS and VTAC conditions and gave our client accurate cost projections to determine if the acquisition made strategic sense.

Value Engineering and Material Selection 

We proposed cost-effective materials that met Marriott's brand standards without inflating costs. A dedicated design and procurement agent joined the team to streamline material selection and keep everything aligned with brand requirements throughout construction.

Phased Construction Approach 

We mapped out a realistic construction schedule with phased execution to meet the December 2024 deadline while minimizing guest disruption. Work was coordinated across trades to maintain quality and safety throughout the occupied property.

Project Description

Axis served as the general contractor following the acquisition. Interior work covered demolition, new flooring, and millwork. Systems work included full plumbing and electrical overhauls as the hotel exterior and parking lot were brought up to standard. We coordinated FF&E warehousing and brought a design and procurement agent onto the team to manage material selection and keep everything aligned with Marriott’s standards.

Guest rooms got new luxury vinyl tile after we removed the old carpet and sheet vinyl, with bathrooms receiving new tile. The biggest challenge was converting 113 tubs to showers. Each one required demolition of the old tubs, waterproofing each room, then installing new surrounds, pans, glass doors, and fixtures. The tubs that remained were refinished and got new valves and trim. 

Throughout the rooms, we scraped popcorn ceilings, primed and painted the surfaces, replacing the corridor vinyl wall coverings. Kitchen areas got smart quartz countertops with light cabinetry touch-ups and new exhaust fans to complete the suite refresh.

Common areas needed attention, too. Corridors got a new carpet and base, while walls, ceilings, and around 480 doors received a fresh coat of paint. Lobby carpet and meeting room flooring were upgraded, and back-of-house spaces were updated. The lobby’s defining feature became a custom barn door we designed for the back desk feature wall. New sconces, pendants, and fixtures throughout guest rooms and corridors brought energy-efficient lighting to the property.

Exterior work tackled the EIFS and VTAC systems that protect the building. We installed head flashing and sill pan flashing on exterior VTACs, applied sealant, and patched EIFS where deterioration had occurred. New VTAC units replaced aging equipment. The parking lot also received comprehensive repairs, restriping, and resealing; this was essential work that had been deferred for too long.

FF&E management ran through our warehouse operations. We liquidated all old furnishings, then coordinated the storage and delivery of new pieces that met Marriott’s standards for guest rooms and public spaces.

Two major hurricanes hit Tampa mid-construction. The supply chains stopped, and labor became scarce as the site flooded and high winds damaged temporary protections. Power outages halted electrical work. 

Axis responded to these challenges by introducing enhanced safety protocols and leveraging pre-purchased materials when our suppliers couldn’t deliver. We also shifted sequencing to interior work, enabling our teams to proceed despite the weather. We compressed the schedule with the Owner’s Representative maintaining close contact with our on-site team for fast decision-making. The project was completed in mid-December 2024.

Project Highlights

Transforming Guest Spaces

Pre-Acquisition Partnership

Our client worked with Axis during due diligence to assess Marriott’s PIP requirements and develop a realistic budget before closing.
From Concept to Completion

Overcoming Hurricane Resilience

Two major hurricanes hit Tampa during construction, but the project stayed on schedule with adjustments and increased safety protocols.

On-Time, On-Budget Execution

Meeting Short Deadlines

The renovation was completed in December 2024, enabling our client to capture Florida’s peak tourist season. 

Transforming Guest Spaces

Barn Door Installation

We designed a custom barn door to be used as the defining centerpiece feature for the back desk feature wall.

From Concept to Completion

Property-Wide Bathroom Conversions

113 tubs were converted to showers with full demolition, waterproofing, and new fixtures, a major undertaking across the entire property.

THE RESULTS

The property opened mid-December 2024, and our client captured the winter season. With a refreshed hotel featuring updated suites with functional kitchens, contemporary bathrooms, custom lobby elements, and a restored parking lot, guest satisfaction scores and RevPAR improved.

Their decision to bring Axis in during due diligence proved essential. We provided accurate cost projections before they closed on the property, giving them the confidence to move forward. When two hurricanes hit mid-construction, the phased approach we mapped out kept work progressing despite the disruptions – and opening on time positioned the hotel to compete effectively in Tampa’s Westshore market during its most profitable season.